Serra de l'Ebre
Needs attentionCatalonia · Wind · 57 MW installed · 5 technicians · manager Firas Cheaib
10.8 MW
19 %
175 MWh
96.6 %
9 / 13
6
Wind
9.2 m/s W
Irradiance
340 W/m²
Temperature
21.4 °C
Cloud cover
39 %
Conditions
Sunny intervals
Substation
Ascó SE 400 kV
Voltage
401.4 kV
Frequency
50.014 Hz
Power factor
0.996
Curtailment
8 %
Day-ahead price
70.01 €/MWh
Assets
13 assets on site. Open one for its live 3D view.
Wind turbine
WTG-03
Siemens Gamesa SG 5.0-145 · 6.2 MW
Output
2.90 MW
Today
32.6 MWh
Wind
9.7 m/s
Wind turbine
WTG-04
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.90 MW
Today
19.0 MWh
Wind
7.7 m/s
Wind turbine
WTG-05
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.00 MW
Today
8.3 MWh
Wind
9.3 m/s
Wind turbine
WTG-07
Siemens Gamesa SG 5.0-145 · 5.0 MW
Output
0.00 MW
Today
21.8 MWh
Wind
10.4 m/s
Wind turbine
WTG-09
Siemens Gamesa SG 6.6-170 · 6.2 MW
Output
0.55 MW
Today
12.3 MWh
Wind
7.9 m/s
Wind turbine
WTG-10
Siemens Gamesa SG 6.6-170 · 4.2 MW
Output
1.79 MW
Today
13.4 MWh
Wind
9.7 m/s
Inverter skid
INV-01
Sungrow SG3125HV-MV · 4.6 MVA
Output
0.55 MW
Today
21.6 MWh
Availability
99.5 %
Inverter skid
INV-02
SMA Sunny Central 4600 UP · 3.1 MVA
Output
0.17 MW
Today
13.1 MWh
Availability
96.3 %
Blade ice detected
Generator winding temperature high
Yaw misalignment above limit
Pitch system hydraulic pressure low
Cooling fan failure
Service interval exceeded